Centercore: The Flexible Datacenter

Fidelity Investments develops a modular datacenter that can grow at 500 kilowatt increments.

When the financial markets began to sour in 2008 during the peak of the global financial crisis, industry heavyweight Fidelity Investments realized it had a datacenter challenge on its hands.

At the time, Fidelity had 82 datacenter locations in North America, with some of the facilities approaching 30 years old. The sprawling technology infrastructure had grown over many years when revenues were constantly increasing and business units were expanding rapidly.

"We needed to get more competitive on IT costs and services," says Eric Wells, VP, data center services, at Fidelity Investments. "Our costs were growing at an unacceptable rate. We also had to get better at deploying applications. Anytime a business unit wanted to do something quickly, it took months to complete."

With many of the older facilities reaching the end-of-life stage for a datacenter and some newer facilities at capacity, Fidelity needed to find a way to incrementally increase datacenter space without overbuilding for today's needs.

Fidelity brought IT and facilities (real estate) leaders together to work on a solution, with the urging of the company's executives, after they saw a Fidelity data center being built. "We thought there could be a better way to build these facilities," says Joe Higgins, VP of engineering and corporate sustainability officer. The goal was to come up with a data center plan that could cut real estate costs by 50% and IT costs by 20%.

Another goal was to come up with a way to build a datacenter to meet capacity needs, but not overbuild for expected needs five or more years down the road, something most traditional datacenter projects try to do. "It is difficult to predict how much capacity you need two years or four years from now," Higgins says. "It is nuts to build big datacenters the old way. Many organizations are building them, but not filling them."

Fidelity wanted to build a datacenter that could be completed in a short period of time, and then have the capability to expand later as computing needs increased. "One of the core tenets of our project was how to deploy a datacenter quickly," Higgins adds. "We wanted to have responsive capacity and to have it available in months. This allows us to have small bets, so if we miss on small bet, it is not as bad as missing on a huge facility."

Fidelity IT and facilities experts sat down and made "literally thousands of decisions" and eventually developed a datacenter that can be built in stages, off-site, and then moved into place, Wells says.

The resulting product is called Centercore. Centercore allows Fidelity to increase space in 500-kilowatt increments, rather than a traditional large datacenter that would be more than a megawatt. Centercore is being used at Fidelity locations in North Carolina in Nebraska to expand the traditional (raised-floor) datacenter facilities.

Centercore can help a datacenter be built much faster, and cheaper, than a traditional datacenter, Fidelity says. "Traditionally, you would take 18 months to build your own facility," Higgins notes. "We can do it in six months, and 10% to 15% cheaper than regular construction." In addition, if a firm were to build a traditional facility, it would "overbuild" for the firm's current needs, since the costs are so high with a traditional buildout.

"I am completely sold that building in increments is the way to go," Wells says. "The unpredictability that exists with technology and in the financial markets" makes it hard to predict what will be needed in the future. "If you are building a huge datacenter, you are spending a lot of capital. Having the ability to spend in increments and evolve with technology, that makes complete sense." Greg MacSweeney is editorial director of InformationWeek Financial Services, whose brands include Wall Street & Technology, Bank Systems & Technology, Advanced Trading, and Insurance & Technology. View Full Bio

Comment  | 
Print  | 
More Insights
Comments
Newest First  |  Oldest First  |  Threaded View
Greg MacSweeney
50%
50%
Greg MacSweeney,
User Rank: Apprentice
1/17/2014 | 7:58:40 PM
re: Centercore: The Flexible Datacenter
A hosted approach may work for some companies. But I think Fidelity thought this would work best with their model, and the restrictions that it has when it comes to client data (and regulatory considerations, as well).
IvySchmerken
50%
50%
IvySchmerken,
User Rank: Author
1/17/2014 | 12:07:44 AM
re: Centercore: The Flexible Datacenter
Capital markets firms still build their own data centers, though some use third party or exchange data centers for hosting their stock trading systems and algorithms to be close to the exchange matching engines. When it comes to confidential customer data, trading positions, and portfolio holdings, this type of proprietary data is held close to the vest.
KBurger
50%
50%
KBurger,
User Rank: Author
1/16/2014 | 8:14:58 PM
re: Centercore: The Flexible Datacenter
And this made more sense for them in terms of cost, speed & flexiblity than a hosted data center approach?
Greg MacSweeney
50%
50%
Greg MacSweeney,
User Rank: Apprentice
1/15/2014 | 11:27:16 AM
re: Centercore: The Flexible Datacenter
Woops. Thanks. Haste makes waste.
Becca L
50%
50%
Becca L,
User Rank: Author
1/14/2014 | 8:47:20 PM
re: Centercore: The Flexible Datacenter
Now wouldn't that be a game-changer! :-)
Joe Brunner
50%
50%
Joe Brunner,
User Rank: Apprentice
1/14/2014 | 4:03:34 PM
re: Centercore: The Flexible Datacenter
I think you meant "500 Kilowatt" increments - lol if Fidelity really had a datacenter that needed "500 Megawatts" they could open their own rather large cloud - several times the size of Amazon :)
joeaffmdsys
50%
50%
joeaffmdsys,
User Rank: Apprentice
1/14/2014 | 4:03:34 PM
re: Centercore: The Flexible Datacenter
I think you meant "500 Kilowatt" increments - lol if Fidelity really had a datacenter that needed "500 Megawatts" they could open their own rather large cloud - several times the size of Amazon :)
Register for Wall Street & Technology Newsletters
White Papers
Current Issue
Wall Street & Technology - Elite 8, October 2014
The in-depth profiles of this year's Elite 8 honorees focus on leadership, talent recruitment, big data, analytics, mobile, and more.
Video
7 Unusual Behaviors That Indicate Security Breaches
7 Unusual Behaviors That Indicate Security Breaches
Breaches create outliers. Identifying anomalous activity can help keep firms in compliance and out of the headlines.